Building permits: PBG and SLF for a new building
What a building approval (PBG) and a certificate of fitness (SLF) are in Indonesia, when each is needed, how to apply and what happens to a building without them.
6 min read
A new building in Indonesia needs two papers from the local government. The building approval (Persetujuan Bangunan Gedung, PBG) comes before construction starts. The certificate of fitness for use (Sertifikat Laik Fungsi, SLF) comes before anyone uses the building.
The PBG replaced the old building permit (Izin Mendirikan Bangunan, IMB). Both papers are set out in Government Regulation 16 of 2021, which implements the Building Law. They’re also basic requirements under the risk-based business licensing rules, so a business that needs a building can’t finish its own licensing without them.
Before the PBG
The PBG comes after the land is secured and the land use is confirmed. The sequence for a company usually runs like this:
- Hold or lease the land on the right title. For a foreign-owned company that’s normally a right to build, as HGB for a foreign-owned company explains.
- Get confirmation that the planned use fits the spatial plan. Warehouses and logistics property shows how that works for one building type.
- Hire a designer, and have the technical plans drawn to the national standards.
- Apply for the PBG.
Buying a plot without checking the first two steps is the usual cause of a building that can’t be permitted.
What the PBG covers
The PBG is needed to build a new building. It is also needed to change, extend, reduce or maintain an existing one. The owner has to apply before construction starts. The application goes to the district or city government, or to the central government for certain special-function buildings.
The PBG fixes the function of the building, such as a house, a shop, a warehouse or a factory. If the function or classification changes later, the owner needs an amended PBG. A warehouse turned into an office, for example, can’t just be refitted.
How the application runs
The application is made online, through the building management information system (Sistem Informasi Manajemen Bangunan Gedung, SIMBG). The owner or applicant registers, enters the details of the owner and the building, and uploads the technical plans. If part of the building is planned to be sold off in units, a unit-division plan is added too.
The process has two parts.
- Planning consultation. Officials and a team of experts check the plans against the technical standards: architecture first, then structure, mechanical and electrical systems and plumbing. The regulation says this consultation costs nothing. It allows at most five rounds of checks within 28 working days, and the first check comes within three working days of registering.
- Issuing. Once the plans are approved, the local government sets the fee, and the PBG is issued after the owner pays it.
The fee is a local levy (retribusi) set by the local government under its own regulation, based on the function and class of the building. It differs from one district to the next, so ask for the figure in the district where you plan to build. The regulation sets the steps, not the length of the whole process, so ask the office what to expect in practice and don’t set a firm date for the start of work until the PBG is in hand.
Other approvals can run in parallel. Depending on its size and type, a project may also need an environmental approval, a traffic study or approvals tied to its business line.
During construction
Work has to follow the approved plans. A change that affects the structure, the function or the floor area needs the plans, and sometimes the PBG, amended first. Keep a record of the contractor, the supervisor and the materials, since the next step asks the owner to show that the building matches what was approved.
The same records matter when a bank is funding the build. Lenders usually release money in stages against the supervisor’s reports.
The SLF
The SLF confirms that the finished building is safe to use and matches its approval. The owner has to hold it before the building is used. The local government issues it after checking the building, and the application also goes through SIMBG. The check covers safety, health, comfort and access, and compares the building as built with the approved plans.
An SLF doesn’t last forever. Under Article 297 of the regulation it has to be extended every 20 years for a single house or a terrace house, and every 5 years for any other building. The extension is preceded by a check of fitness for use, which compares the building and its as-built drawings with the last SLF and with the technical standards. If the drawings differ from what stands on the site, the owner has to correct them first.
For a warehouse, factory, shop or office, that means a recurring inspection every five years, and a cost and a date to put in the owner’s calendar.
What the SLF is used for
Buyers, tenants, banks and insurers ask for it. A building without an SLF is harder to let, to insure and to sell. The regulation also ties the building ownership certificate (Surat Bukti Kepemilikan Bangunan Gedung, SBKBG) to the PBG number and the SLF number, so the building’s papers refer back to both.
For apartments, the SLF is also a condition for the final sale deed, as buying from a developer explains. A buyer who is shown a finished building without an SLF should ask why.
Buildings that lack the papers
The regulation gives local governments a list of administrative sanctions for owners who don’t follow their approval. The list runs from a written warning, through limits on construction or a stop to the work or to the use of the building, to freezing or revoking the PBG or the SLF and, at the end, an order to demolish.
Older buildings need care. A building put up under an old IMB, or with no permit at all, doesn’t automatically meet today’s standards. If you’re buying one, ask for whatever permit exists and have an engineer check the building. Don’t assume the seller’s paperwork can be fixed after the sale, and write the point into the contract as a condition.
Checks before you build or buy
- Confirm that the land title, the spatial plan and the planned use match, before the land is paid for.
- Ask the district office for the PBG fee rules and the documents it wants.
- Have the plans drawn to the national standards by a qualified designer.
- Don’t start construction before the PBG is issued.
- Keep as-built drawings and the supervisor’s records for the SLF.
- When buying a finished building, ask for both the PBG and the SLF, and note the date the SLF falls due for extension.
- Add the fee and the inspection costs to the budget, next to the taxes in purchase costs and taxes.
- Have a local lawyer or notary read the documents before you sign.
General information, not legal, tax or investment advice. Rules change, so confirm the current regulation with a notary or lawyer before you act.