Electricity is easy to take for granted in a city and hard to find at a remote site. In Kalimantan the question is rarely whether power exists. It’s whether it reaches the site, in the amount needed, at a price that works.
A project has three broad options: connect to the state utility PLN, generate its own power, or do both. Each comes with different costs and different paperwork.
The grid in Kalimantan
PLN (Perusahaan Listrik Negara) owns the main grid and most distribution lines. Kalimantan isn’t one grid. In March 2025 the energy ministry described two main systems: the Khatulistiwa system in West Kalimantan and the interconnected system covering the rest of the island. PLN is building lines to join them. In the same statement, PLN data put dependable capacity across Kalimantan at 3,334 MW against a peak load of 2,412 MW.
The numbers say the main grid has room. They don’t say the line near your site does. Beyond the main corridors, many districts run on local systems, some of them diesel plants (PLTD) that PLN is slowly replacing or linking in. In such places, supply can be thin, and a big new customer may find that the local line can’t carry the load.
So the first question is local. Ask PLN’s regional office whether the nearest line has the capacity, how far it is, and what connection would cost. The answer for a plant 2 km from a substation is very different from one 30 km away. Selling a palm oil mill’s surplus power to PLN describes the same issue from the supplier’s side.
What a connection involves
A new customer applies to PLN for a connection at a given capacity. PLN studies the site, then sets the voltage, the equipment and the connection charge. Large industrial users connect at medium or high voltage and usually pay for the line and the transformer they need. Timing depends on the line works and on land for the right of way, and PLN’s estimate should be written down.
Three points are worth settling early.
- Reliability. Ask how often the line trips, and whether the site would sit at the end of a long feeder. A cold store, a mill or a smelter can lose a lot in one outage.
- Quality. Voltage drops on long rural lines can damage motors and electronics.
- Tariff class. The class decides the price per kWh and any minimum charge. Check it against your actual load pattern.
Generating your own power
Many projects in Kalimantan run their own generators, either as the main source or as a back-up. A diesel set is the common answer for a camp, a small plant or a remote mine. Larger sites might build a gas, coal or biomass plant. Palm oil mills already burn fibre and shells to run themselves, as the article on palm kernel shells and the one on mill power explain, and biogas from mill effluent describes another source.
Own generation avoids the wait for a connection. The costs move elsewhere: fuel, which has to be trucked or barged in, spare parts, operators and the capital for the plant itself. Fuel logistics are tied to roads and rivers, so Kalimantan’s infrastructure matters here too.
A plant built for the owner’s own use is called a captive plant. In law it’s separate from a plant built to sell electricity to the public.
Permits for captive generation
Electricity supply in Indonesia is a licensed business under the Electricity Law. The licence for generating power for your own use is the IUPTLS (Izin Usaha Penyediaan Tenaga Listrik untuk Kepentingan Sendiri). Rules are in Energy and Mineral Resources Ministry Regulation 11 of 2021, and the licence is applied for through the online licensing system (OSS).
What the 2021 regulation says:
- A business supplying electricity for its own use must hold an IUPTLS (Article 39).
- Only a business entity can hold one (Article 9). A company, not an individual.
- It lasts up to 10 years and can be extended (Article 40).
- It must be amended if the use or the installed capacity changes (Article 41).
The ministry’s guidance puts the threshold at 500 kW of generating capacity in one installation. Above that you need an IUPTLS, and below it you report the plant to the authorities. Confirm the present figure and the report rules with an adviser, because this part of the rules has been changed before and may change again.
A licence to sell power to the public is a different thing. An integrated electricity supply business licence (IUPTLU) holder has an exclusive service area (wilayah usaha). A captive plant can’t sell to customers inside that area. It can sell its surplus to the area’s licence holder, usually PLN, under the excess power rules, as Article 59 of the regulation describes. Supplying neighbours or tenants is a different business. An estate that sells power to its tenants needs the right supply licence, so ask an adviser which one applies.
The plant also needs the usual project approvals: a site that fits the spatial plan, as covered in spatial planning approval, an environmental approval, and building and fire safety approvals for the structures. A plant that burns coal or biomass needs air emission controls, and a plant with a jetty for fuel needs a terminal approval.
Choosing between them
There’s no single right answer. A few rules of thumb help.
- If a reliable PLN line is close, connect, and keep a generator for back-up.
- If the line is far, compare the cost of building the connection with the cost of fuel, operators and a plant over the project’s life.
- If the load is steady and large, own generation can pay, but only if fuel supply is secure.
- If the site produces its own fuel, such as shells, fibre or gas, own generation is easier to justify.
Industrial estates are another route, since power is one of the things a tenant checks. Industrial and warehouse land near Kalimantan’s ports covers what to ask an estate about power and water.
Before you commit
- Get a written statement from PLN’s regional office on the nearest line, available capacity, connection cost and timing.
- Ask for the line’s outage record, not just the promise.
- If you plan to generate, price fuel delivered to the site, and decide who runs and maintains the plant.
- Check whether the plant’s size needs an IUPTLS, and who will apply for it.
- If surplus power is part of the plan, confirm with PLN that it wants to buy it before any equipment is ordered.
General information, not legal, tax or investment advice. Rules change, so confirm the current regulation with a notary or lawyer before you act.