Spatial planning approval (KKPR/PKKPR) for a project site

What the spatial approval is, how the RDTR decides the route to it, how marine space is handled and why it comes before the other permits for a site in Indonesia.

5 min read

Before a company builds a factory, a plantation office, a jetty or a hotel in Indonesia, the site has to fit the spatial plan. The approval that confirms this is called KKPR, short for Kesesuaian Kegiatan Pemanfaatan Ruang, or suitability of a land-use activity with the spatial plan. You’ll also see PKKPR, the Persetujuan KKPR, which is one of its two forms.

A land certificate doesn’t answer this question. A plot can be freely owned and still sit in a zone where your use isn’t allowed. The approval is how a buyer finds that out before paying for the land.

Where it fits

KKPR is the first step in the licensing chain for a physical project. Other approvals follow it: the environmental approval, the building permit (PBG) and the certificate of fitness (SLF). It replaced the old location permit (izin lokasi) as the way a business shows that a site suits its use.

For businesses it runs through the online licensing system (Online Single Submission, OSS). Government Regulation 21 of 2021 set up the system, and Government Regulation 28 of 2025 on risk-based licensing now carries the KKPR rules, with a transition period for the move. Rules in this area have changed several times since 2020, so check the current text before applying.

Two routes: RDTR or no RDTR

A spatial plan exists at several levels. The national, provincial and regency plans are broad. The detailed spatial plan (Rencana Detail Tata Ruang, RDTR) is the one that works plot by plot. It says what each zone allows, how much of a plot can be built on and how tall a building may be.

The route to approval depends on whether the area has an RDTR in the system.

  • Konfirmasi KKPR. Where a digital RDTR is available in OSS, the system checks the site against it. If the use matches, you receive a confirmation, with no long assessment.
  • Persetujuan KKPR (PKKPR). Where there’s no RDTR, the site is assessed against the broader plans. The land office gives a technical opinion, and the approval may come with conditions.

For an investor, that means the same project can take very different routes on two sites. A plot in a town with a detailed plan is quick to check. A plot in a district without one needs an assessment, and the outcome is less certain. Don’t rely on a time estimate from a seller. Ask the district’s spatial planning office, or an adviser who has filed in that district recently, what the process is at present.

Both forms record the same kind of facts: the permitted use, the allowed share of the plot you can build on and the floor area. They also tie the approval to the plot’s coordinates, so the application has to show the right map.

Marine space: KKPRL

A project in coastal waters or at sea needs a separate approval for the use of marine space, the KKPRL (Kesesuaian Kegiatan Pemanfaatan Ruang Laut). In Kalimantan this matters for jetties, loading terminals, water intakes and outfalls, pipelines, fish farms in cages and similar structures. It’s applied for through OSS as well, and the marine ministry’s plans decide the outcome. Some areas, such as conservation zones, need extra recommendations before an approval can be given.

A site on a river bank can involve both. The land side needs a KKPR. The structure over the water may need marine space approval, plus a port or terminal approval from the transport ministry, as hauling, barging and ports describes for coal jetties.

What the approval doesn’t do

KKPR doesn’t prove ownership, doesn’t release forest land, and doesn’t replace other licences.

  • It doesn’t confirm the land is yours. Titles are covered in land rights in Indonesia, and a certificate should be checked as checking a land certificate explains.
  • It doesn’t change forest status. A plot inside a designated forest area needs forestry decisions on top, as forest area status explains. The spatial plan and the forest map don’t always agree, so check both.
  • It doesn’t cover a protected farmland zone. Protected farmland (LP2B) can block a conversion even where other plans seem to allow it.
  • It doesn’t replace the environmental approval or the building permit. Those come after it and need the approval first.

Customary or village land inside the site is a separate matter again, and customary land and communities covers it.

Common problems

  • A buyer assumes that a plot beside a factory is also zoned for industry. Zones change from one plot to the next.
  • The approval is for one use. If the project later changes, for example from a warehouse to a processing plant, the approval may need to be changed.
  • The approval was issued for a different company or a different set of coordinates from the ones in the deal.
  • Land was bought on the strength of a seller’s promise that the permit would follow. If the plan doesn’t allow the use, the permit can’t be issued, and the buyer holds land it can’t use as planned.

Before you sign

  1. Ask the district’s spatial planning office, or check the plan, which zone the plot sits in and whether an RDTR exists.
  2. Compare that zone with your intended use, including the share of the plot you may build on.
  3. Make a KKPR or a konfirmasi KKPR for your exact use a condition of completing the purchase, with the right to withdraw.
  4. Check the plot against the forest map and the farmland map in the same pass.
  5. If anything touches water, find out early whether a marine space approval is needed.

Industrial and warehouse land near Kalimantan’s ports shows how the approval works on industrial estates, where a tenant’s use is often covered by the estate’s own approvals. A foreign-owned company applies through the same system once it exists, as setting up a PT PMA explains.

General information, not legal, tax or investment advice. Rules change, so confirm the current regulation with a notary or lawyer before you act.