Gold exploration stages: from first samples to a feasibility study

How a gold project moves from grassroots work to drilling, resource estimates and feasibility, what each stage costs in time and why so few prospects become mines.

6 min read

A gold project is worth what it has proved so far. A ridge with old workings and a few rich rock samples is one thing. A drilled deposit with a resource estimate is another, and a deposit with a feasibility study and a production licence is a third. Each step costs more than the one before, and each one can end the project.

Knowing which stage a project has really reached tells you most of what you need about its risk and what it can fairly be priced at. Sellers tend to describe their project one stage further on than it is.

Grassroots exploration

Exploration starts with ground that nobody has tested well. Geologists read old maps and reports, satellite images and any geophysical data, then go into the field. They map the rocks, take stream sediment samples to see which rivers carry gold, and sample soils on a grid to find where the signal comes from. They chip rock from outcrops and old diggings and send it to a laboratory.

In Kalimantan this work is slow. Outcrop is scarce under thick soil and forest, many areas are reached only by river or on foot, and heavy rain cuts tracks for weeks. Local diggers are often the first clue. Their pits show where gold has been found, though not how much there is.

This stage is cheap compared with what follows, and most projects never get past it. The anomalies fade on closer sampling, or the rocks turn out to be the wrong kind. A report at this stage can describe results and, at most, an exploration target stated as a range. It can’t give a resource. The article on gold resources and reporting explains the codes that set those limits.

Trenching and first drilling

When soil and rock results point to a zone, the next step is to see it below the surface. Trenches dug across the zone expose the rock for mapping and channel sampling. Geophysics, such as induced polarisation or magnetic surveys, helps trace structures that might carry gold under cover.

Then comes the first drilling. Diamond drilling cuts a solid core that geologists can log and split for assay. Reverse circulation drilling returns chips. It’s faster and cheaper per metre but tells you less about the rock. A first programme might be a handful of holes aimed at the best targets. The question it answers is simple: is there gold at depth, in widths and grades that could matter?

Many projects stop here too. A good surface showing can come from a thin vein, a small pocket or gold concentrated by weathering near the surface, and it can thin out or vanish a short way down.

Resource drilling

If the first holes hit, the work changes from finding to measuring. Holes are drilled on a regular grid, tightened step by step, so a geologist can model the shape of the mineralised body and estimate its tonnes and grade. Samples go through quality control, with standards, blanks and duplicates, and a share are rechecked at a second laboratory.

The output is a mineral resource estimate signed by a competent person, in categories that rise with confidence: inferred, then indicated, then measured. Moving material from inferred to indicated usually means drilling the same ground again at closer spacing. That’s the most expensive part of exploration, and it’s where a project’s value starts to firm up.

Alongside the drilling, the project starts collecting what later studies need: samples for metallurgical tests, water and weather data, environmental baselines and the first social mapping of nearby villages. How the ore will respond to processing matters as much as the grade. The article on gold processing methods covers why.

Scoping, pre-feasibility and feasibility

Studies turn a resource into a possible mine. They follow a sequence, each more detailed and more costly than the last.

  • A scoping study, sometimes called a preliminary economic assessment, gives a first view of whether a mine could work. It can use inferred material, and its cost estimates are rough.
  • A pre-feasibility study compares options for mining method, plant size, processing route and site layout, and picks one. It’s the first study that can support a probable reserve under the reporting codes.
  • A feasibility study designs the chosen option in enough detail for a decision to build and for lenders to assess. Its capital and operating cost estimates are much tighter than a scoping study’s.

Each study also tests the economics: gold price, grade, recovery, strip ratio, costs and the state’s take. The article on gold project economics shows how to read those numbers.

The Indonesian licence path

Under the Mining Law (Law 4 of 2009 as amended by Law 3 of 2020), a mining business licence (Izin Usaha Pertambangan, IUP) has an exploration stage and a production stage. The exploration stage covers general survey, exploration and the feasibility study. Moving to production needs an approved feasibility study and environmental approval, which for a mine of any size means an environmental impact assessment (Analisis Mengenai Dampak Lingkungan, AMDAL).

Each year the holder needs an approved work plan and budget (Rencana Kerja dan Anggaran Biaya, RKAB), annual again from 2026, and it reports its exploration results to the energy ministry. Exploration licences carry a fixed term. If the work isn’t done and the licence isn’t raised to production in time, the area can be lost. Check the term and expiry on the licence itself, and confirm current rules with the ministry or a mining lawyer, since they changed often in 2025 and 2026. The article on buying into a gold mining licence covers the licence checks in detail.

Forest status matters early. Drilling inside a designated forest area needs a forest area use approval, and without it even exploration is exposed.

Time and odds

Exploration is a long game. Taking a discovery through resource drilling and studies to a decision to build commonly takes the better part of a decade, and longer where access, permits or community relations are hard. Financing usually comes in rounds, each one sized to reach the next result.

The odds are poor at the start and improve with each stage passed. Most grassroots prospects never get a drill hole, most drilled prospects never get a resource, and many deposits with a resource are never mined because grade, metallurgy, location or cost don’t add up. Kalimantan’s Busang fraud of the 1990s, where samples were salted, is the extreme case of why every stage needs checking. The quieter risk is ordinary: honest projects that simply don’t work.

That’s why price follows stage. An early project with good geology but no drilling is an option on future work, not a deposit. Paying for it as if the deposit were proved is the most common mistake in gold deals.

What to check first

Ask the seller to place the project on this ladder and show the evidence for that stage:

  • The licence, its stage and expiry date, checked against the ministry’s records, and the forest status of the area.
  • Every assay result, not only the best ones, with maps showing where each sample and hole sits.
  • Drill logs, core photos and the quality control data, and whether core is still stored and available to inspect.
  • Any resource estimate, with the competent person’s name, registration and consent.
  • Metallurgical test results, even preliminary ones.
  • The budget and timetable for the next stage, and what result would justify going beyond it.

If you’re buying in, tie payments to milestones that match these stages. An earn-in or staged joint venture, covered in gold project partnerships, is built for this.

General information, not legal, tax or investment advice. Rules change, so confirm the current regulation with a notary or lawyer before you act.