Environmental approvals: AMDAL, UKL-UPL and SPPL

How Indonesia's environmental approval works for a plantation, mill, mine or factory: the three instruments, which one applies, technical approvals and common delays.

6 min read

An Indonesian business licence for a plantation, a mill, a mine or a factory doesn’t stand alone. It rests on an environmental approval (persetujuan lingkungan). Without that approval the licence isn’t issued, and a project that has started without one can be stopped.

The approval comes in three grades, named after the document behind each: AMDAL, UKL-UPL and SPPL. Which grade a project needs depends on how large its environmental impact could be. This article explains what the three are, how the choice is made and where projects lose time.

The framework is Government Regulation 22 of 2021 on environmental protection and management, in force since 2 February 2021. It implements the Job Creation Law and replaced the old environmental permit (izin lingkungan) with the environmental approval. It also folded several older regulations on water, air, marine pollution and hazardous waste into one text.

Two points from the regulation matter most to an investor:

  • The environmental approval is tied to the business licence. Under the risk-based licensing rules, Government Regulation 28 of 2025, the approval is one of the basic requirements that come before the licence.
  • Enforcement starts with administrative sanctions. The regulation treats criminal enforcement as a last resort, but administrative sanctions can still include suspension and revocation.

Since October 2024 the environment has had its own ministry, separate from forestry. Environmental approvals are now the environment ministry’s job, and forest status is a forestry matter, as forest area status explains.

The three instruments

AMDAL

The environmental impact analysis (Analisis Mengenai Dampak Lingkungan, AMDAL) is the heaviest. It is required for activities with a significant impact on the environment. It has three parts:

  • A terms of reference (Kerangka Acuan), which fixes what the study will cover.
  • The impact analysis itself (Analisis Dampak Lingkungan).
  • The environmental management and monitoring plans (Rencana Pengelolaan Lingkungan and Rencana Pemantauan Lingkungan, RKL-RPL).

An AMDAL has to be prepared by people with the right certification, assessed by a review body and open to comment from the people affected. The outcome is an environmental feasibility decision, and the environmental approval is then issued on it.

UKL-UPL

The environmental management and monitoring effort (Upaya Pengelolaan Lingkungan dan Upaya Pemantauan Lingkungan, UKL-UPL) is the middle grade. It is for activities that aren’t expected to have a significant impact but aren’t small enough for a simple statement. It is a standard form, filled in at the planning stage, that must match the spatial plan. It is checked, and the approval is issued on a recommendation.

SPPL

The statement of commitment to manage and monitor the environment (Surat Pernyataan Kesanggupan Pengelolaan dan Pemantauan Lingkungan, SPPL) is a self-declaration. It is for activities that fall below both of the other thresholds, and for micro and small businesses with no significant impact. The company states what it will do. Nobody assesses it first.

InstrumentForWhat happens
AMDALSignificant impactFull study, review, feasibility decision
UKL-UPLImpact that is not significantStandard form, checked, recommendation
SPPLLowest impactSelf-declaration through the licensing system

What decides the grade

A ministerial regulation, Environment and Forestry Ministry Regulation 4 of 2021, lists the types of business and activity that need an AMDAL, a UKL-UPL or an SPPL. The annex sets thresholds by activity: area in hectares for a plantation or a mine, capacity for a mill or a factory, length for a road, and so on. Activities that fall under none of the thresholds get the lighter grades.

The thresholds are numbers that change by sector, so don’t rely on a rule of thumb you heard for plantations. Look up the activity in the annex, using the same code the company holds in OSS.

Under the 2025 licensing rules, the grade is now found through screening. An application for a business identification number in OSS leads into the environmental ministry’s online platform, Amdalnet, where the activity is screened and the system says whether it needs an AMDAL, a UKL-UPL or an SPPL. Amdalnet runs the later stages too: preparing, assessing and issuing. A low-risk business no longer gets an SPPL automatically with its number.

Two other things can push a project up a grade:

  • Location. The criteria for a significant impact look at the site as well as the size, so a project near a protected area, a peatland or a river deserves a closer look than its size alone suggests.
  • Scale. Expanding an existing site or adding a new phase can cross a threshold the first phase didn’t.

Technical approvals and the spatial plan

The environmental approval isn’t the only environmental paper. Activities that discharge waste water, emit air pollution or handle hazardous waste also need a technical approval (persetujuan teknis). The environmental approval and the technical approval are now processed in parallel, but discharging, emitting or handling hazardous waste can only begin once the technical approval is issued.

The approval also depends on the spatial plan. Without the spatial-use approval (KKPR on land, or its marine counterpart for coastal waters), the environmental approval can’t be issued. Industrial land near ports describes the zoning step for coastal sites.

Which office issues the approval depends on the location and scope of the activity. The ministry has described the transfer of that authority between central and regional offices as still in transition, so ask the licensing authority where your file will be decided.

Where projects lose time

  • A site bought before the approval. The land is paid for, then the study shows a protected area, a peat dome or a village within the footprint.
  • A change of plan. An AMDAL covers the activity as described. A larger mill, a new product or a different site usually means revising the document or filing a new one.
  • Public consultation. Villages that weren’t asked, or were asked late, can object. Customary land and communities explains why this is a real risk for plantations and mines.
  • Missing reports. The management and monitoring plans have to be carried out and reported. Supervisors check them, and gaps show up in a sale.

What to check when buying into an existing project

  1. Ask for the environmental approval and the documents behind it: the AMDAL, the UKL-UPL or the SPPL.
  2. Compare the approval’s scope with what stands on the ground. A mill or an estate that has grown past what the document describes is out of compliance.
  3. Ask for the monitoring reports that were filed and any notice from the environment authority.
  4. Check that the technical approvals exist for waste water, emissions and hazardous waste, as palm oil mills and fruit notes for mills.
  5. Read plantation permits and HGU next, for the order in which a plantation’s approvals come.

An approval issued to one company doesn’t pass to a buyer by itself. Whether it can be transferred or must be reissued depends on how the deal is built, and an adviser should confirm that before signing.