Business licences under OSS: KBLI codes and risk levels

How Indonesia's online licensing system sorts business activities by KBLI code and risk level, what each level needs, and the 2025 regulation that now governs it.

5 min read

Every business in Indonesia is licensed through one online system, Online Single Submission (OSS). The system doesn’t ask what kind of company you are. It asks what you will do, and it sorts each activity by a code and a risk level. Those two things decide which licences you need, who issues them and whether you can start trading before they arrive.

For a foreign investor in Kalimantan, the codes also decide the ownership rules. Getting them right at the start saves an amendment of the company’s articles later.

The rule that applies now

Risk-based licensing was introduced by Government Regulation 5 of 2021. That regulation has been replaced. Government Regulation 28 of 2025 on the implementation of risk-based business licensing was enacted and took effect on 5 June 2025, and the official regulation database lists it as in force and Regulation 5 of 2021 as revoked.

The new regulation keeps the structure of the old one: activities sorted by risk, an identification number for every business and licences that scale with risk. It changes some things around the edges:

  • It splits the process into starting a business and running it. Starting covers setting up the legal entity, the basic requirements and the licence. Running has a preparation phase and an operational phase.
  • It brings more sectors into the risk-based system, from 16 to 22 according to a law firm’s reading of the text.
  • It adds a general set of administrative sanctions, applied through OSS: warnings, temporary suspension, fines, coercive measures and revocation.
  • It bars regional governments from adding requirements of their own to the national rules. The government has said the regulation is the single legal reference for risk-based licensing.

Old guides, including many written for investors, still cite Regulation 5 of 2021. Treat anything that quotes it as out of date until you’ve checked it against the 2025 text.

KBLI: the code behind every activity

Every activity has a five-digit code in the Indonesian standard industrial classification (Klasifikasi Baku Lapangan Usaha Indonesia, KBLI), kept by the statistics agency. The current edition is the 2020 one.

Two examples from Kalimantan: an oil palm estate sits under KBLI 01262, and a palm oil mill under KBLI 10431. Different codes mean different licences, different agencies and sometimes different ownership rules. The positive investment list is written against these codes too.

Some practical points on choosing them:

  • Pick the code that describes what the company will actually do, not the broadest one on offer.
  • A company can hold several codes. Each one is licensed and reported separately.
  • The codes go into the deed of establishment and onto the business identification number (Nomor Induk Berusaha, NIB). Adding or changing one later means amending the articles.
  • A licence is tied to a code. A trading company can’t run a plantation because the owner has the right land.

OSS has a public tool that takes a code and shows the permits it needs, so you can check a code before you commit to it.

The four risk levels

Each activity is placed in one of four levels. The level sets the paperwork.

Risk levelWhat it needs
LowThe NIB only
Medium-lowThe NIB and a standard certificate, based on the company’s own statement
Medium-highThe NIB and a standard certificate, verified by the authority
HighThe NIB and a business licence, often with an environmental impact assessment

A low or medium-low activity can start once the NIB is issued. A medium-high or high one has to obtain its certificate or licence, or meet its commitments, first. Plantations, mills and mines sit at the demanding end and need full licences.

The NIB is the company’s identity in the system, and the number to ask for when you check a counterparty. Checking an Indonesian company shows how.

The basic requirements come first

Before a licence can be issued, most activities need the location and the environment cleared. The regulation calls these the basic requirements:

  • Spatial-use approval (Kesesuaian Kegiatan Pemanfaatan Ruang, KKPR), which confirms the site is zoned for the activity.
  • Environmental approval (persetujuan lingkungan), described in environmental approvals.
  • For buildings, a building approval (PBG) and a certificate of fitness (SLF).

Together with the business licence, these are the steps where a project stalls. A code that looks easy can still need a site that the spatial plan doesn’t allow.

Time limits and deemed approval

The regulation sets a time limit for each stage, from registration to issue. The government has said, for example, that the spatial-use assessment by the land ministry is capped at 25 working days without revisions and 40 with them. The rule that a licence is deemed approved when the authority misses its deadline carried over from the Job Creation Law.

Treat the limits as a tool for chasing an office, not as a forecast. Real timing depends on the complete file, on the site and on the agency. Don’t start building or planting on a deemed approval without a written record from OSS.

After the licence: reports and supervision

A licence is not the end of the paperwork. A foreign-owned company files an investment activity report (Laporan Kegiatan Penanaman Modal, LKPM) every quarter, per activity and per location, as setting up a PT PMA explains. The 2025 regulation also puts weight on continuing compliance: authorities supervise through OSS and can apply sanctions in tiers, up to revocation.

Keep the full set of approvals, maps and reports for each activity in one file.

A short checklist

  • Decide the codes before the deed is signed, and check each in OSS for its risk level and for the foreign ownership rule.
  • Read the 2025 regulation, or an adviser’s note dated after 5 June 2025, not an older guide.
  • Map the basic requirements for each site: spatial-use approval, environmental approval and, for buildings, PBG and SLF.
  • Keep the NIB, certificates and licences consistent in name and code with the deed.
  • Calendar the quarterly LKPM from the day the NIB is issued.
  • Confirm anything unclear with the Ministry of Investment and Downstream Industry or an Indonesian corporate lawyer.

General information, not legal, tax or investment advice. Rules change, so confirm the current regulation with a notary or lawyer before you act.