Coal downstreaming: gasification, DME and the royalty incentive
What Indonesia means by coal downstreaming, from gasification and DME to briquettes and upgrading, the 0% royalty incentive and why so few projects have been built.
6 min read
Indonesia wants more of its coal turned into products at home rather than shipped raw. The policy is called downstreaming (hilirisasi), and it already reshaped nickel, where export bans pushed miners to build smelters. For coal the push has been slower, and the results so far are mostly plans.
For an investor in a coal mine, downstreaming matters in two ways. Some licence holders are required to do it. And a downstream project can change the state’s take on the coal it uses. Neither should be taken at face value without checking the current rules and the state of the projects involved.
What counts as downstreaming
The Mining Law (Law 4 of 2009 as amended by Law 3 of 2020) asks holders of production licences to increase the value of the coal they mine, through development or utilisation inside Indonesia. The activities the rules list include:
- Upgrading, which dries low-rank coal to raise its calorific value.
- Making briquettes.
- Making coke for steel and other industry.
- Liquefaction, turning coal into liquid fuels.
- Gasification, including underground gasification, turning coal into a synthesis gas that can be made into methanol, dimethyl ether (DME), ammonia and other chemicals.
- Coal slurry or coal-water mixtures for fuel.
Burning coal in a power plant at the mine mouth has also been treated as a form of utilisation in some contexts. Check how the ministry classes a given project before relying on it.
Who has to do it
The obligation falls hardest on the former coal contract holders. When a coal contract of work (Perjanjian Karya Pengusahaan Pertambangan Batubara, PKP2B) ends and continues as a special mining business licence (IUPK), the holder has to carry out coal development or utilisation inside Indonesia as a condition. The first-generation contracts, which include several of Kalimantan’s largest mines, all converted between 2020 and 2025. The article on coal licences covers that conversion.
Those companies submit downstreaming plans to the energy ministry, and their progress is part of what the ministry reviews. For a company holding an ordinary mining business licence (IUP), downstreaming is encouraged rather than tied to the licence in the same way. Ask a mining lawyer what applies to the specific licence in front of you, since the implementing rules have changed several times.
The 0% royalty incentive
The Job Creation Law of 2020 added a provision to the Mining Law that lets a production-stage IUP or IUPK holder that carries out coal downstreaming receive special treatment on its payments to the state, including a royalty of 0% on the coal used for that downstreaming. The details, such as which projects qualify, how much coal counts and from when, are left to implementing regulations.
That incentive can be large on paper, since royalty is one of the biggest charges on coal (see royalties and taxes on coal). It applies only to the coal that actually goes into a qualifying downstream project, not to the mine’s export sales, and it depends on the project being approved and running. As of 2026, confirm with the energy ministry or a tax adviser whether the implementing rules are in force, what conditions they set and whether any project has received the incentive.
Gasification and DME
The flagship idea has been gasifying coal to make DME, a fuel that can replace part of the liquefied petroleum gas (LPG) Indonesian households cook with. Indonesia imports most of its LPG, so replacing it with a product made from domestic coal fits the government’s aims on both trade and energy security.
The best-known project shows how hard this is. State coal miner PT Bukit Asam signed with the American gas company Air Products to build a coal-to-DME plant at Tanjung Enim in South Sumatra, and the president broke ground on it in January 2022. Air Products withdrew from Indonesian coal gasification in 2023. Officials have kept coal-to-DME on lists of priority downstream projects since then, and new partners and funding routes have been discussed, but you should check the current status of any named project before relying on it.
In Kalimantan, former contract holders have announced plans for coal-to-methanol and other gasification projects, linked to their IUPK obligations. Several have been announced more than once with changing partners and timetables. Treat any such plan as uncertain until it has financing, a contractor and an offtake agreement.
Why so few projects get built
Gasification plants are large chemical plants. They cost billions of dollars, take years to build and need a reliable supply of coal, water and power. Their product has to compete on price with what it replaces: LPG, methanol from natural gas, or imported chemicals. When oil and gas prices fall, the economics weaken.
Emissions are a second barrier. Turning coal into chemicals or fuel releases more carbon dioxide than many alternatives, and a growing number of international banks, insurers and technology suppliers limit their exposure to coal (see coal and the energy transition). That narrows the pool of partners and finance.
Third, the products may need subsidies or a committed state buyer. DME priced to replace subsidised LPG, for example, needs a government decision on who pays the difference and who buys it.
Smaller forms of downstreaming, such as briquettes, upgrading and coking, are more achievable, but their markets are narrow, and upgraded low-rank coal can be harder to store and ship.
What it means for a mine investment
For most investors buying into a Kalimantan coal mine, downstreaming is a compliance question rather than an opportunity. A former contract holder’s licence comes with a commitment, and a missed or stalled project can draw attention from the ministry when it reviews the company’s plans. An ordinary IUP is less exposed but may face new rules if policy tightens.
As a direct investment, a downstream coal project carries all the risks of a large chemical plant plus the policy risk of coal. It suits investors with deep technical skills, long horizons and a clear route to offtake. Low-rank coal is the usual feedstock, so the quality of the mine’s coal, covered in coal quality and specifications, feeds straight into the plant design.
What to check first
If downstreaming comes up in a coal deal, ask for these:
- The licence type and whether it carries a downstreaming obligation, with the relevant decree and any approved plan.
- The ministry’s latest review of that plan and any warnings or conditions it raised.
- For any named project: the partners, the technology supplier, the feedstock and offtake agreements, and the financing in place.
- Whether the company has applied for or received the 0% royalty treatment, and on what terms.
- How much coal the project would take from the mine each year, and how that affects export volumes and the domestic market obligation.
Then value the mine on its coal sales under current rules, and treat any downstream project as a separate case that has to prove itself.
General information, not legal, tax or investment advice. Rules change, so confirm the current regulation with a notary or lawyer before you act.