A food processing plant in Kalimantan sits between two hard problems. On one side, it needs a steady supply of raw material from farms, boats or ships, in the right quality and at a price that works. On the other, it needs to get its product to buyers who are far apart and often closer to Java than to each other.
The plant itself is usually the easier part. Equipment can be bought and installed. What decides most projects is the site, the licences and the supply, and they have to be worked out together before money goes into a building.
Choosing the site
The Industry Law (Law 3 of 2014) requires a factory to be inside an industrial estate, with exceptions. A plant can sit outside one where the district or city has no estate or no plots left, as long as it’s in an area the spatial plan sets aside for industry. Small and medium plants that don’t risk widespread pollution are exempt too, as are plants that need to be close to a special raw material, such as a fish plant on the coast.
That last exception matters for food. Many plants process raw material that spoils quickly, so they’re built near the farms, the ports or the landing sites. A fish cold store and processing plant belongs at a fishing port. A rice mill belongs near the rice fields. A plant that handles imported or shipped-in ingredients, such as flour or sugar, makes more sense near a seaport.
Whatever the location, the land must be zoned for the use. Check that it isn’t protected farmland or designated forest area. The articles on industrial land near the ports and on protected farmland (LP2B) explain those checks.
Who can own the plant
Most food processing is open to foreign investment through a foreign-owned company (Perseroan Terbatas Penanaman Modal Asing, PT PMA). Some business lines are reserved for small local businesses or open to foreign investors only in partnership with them. These tend to be traditional products made at small scale, but the list is set by business classification code (Klasifikasi Baku Lapangan Usaha Indonesia, KBLI), so check each code you plan to use. The article on the foreign investment positive list explains how.
A PT PMA has to meet a minimum investment value, which has been set at more than 10 billion rupiah per business line per location, not counting land and buildings, with a minimum paid-up capital set separately by the investment ministry. These figures have been revised in recent years, so confirm the current ones before you plan your capital. The investment ministry publishes the current figures.
A PT PMA can’t own land outright. It can hold a right to build (Hak Guna Bangunan, HGB), either directly or on top of an estate operator’s right of management, or it can lease.
The licences, in order
Business licences in Indonesia are issued through the online licensing system (Online Single Submission, OSS) on a risk-based model. The rules were reissued in 2025 as Government Regulation 28 of 2025, which replaced Government Regulation 5 of 2021. Food processing is usually rated medium-high or high risk, which means more than a registration number.
The usual sequence is:
- A business identification number (Nomor Induk Berusaha, NIB) for the company, tied to its KBLI codes.
- A spatial-use approval (Kesesuaian Kegiatan Pemanfaatan Ruang, KKPR) for the site.
- An environmental approval: an environmental impact assessment (Analisis Mengenai Dampak Lingkungan, AMDAL) for large plants, an environmental management and monitoring plan (UKL-UPL) for medium ones, or a statement letter for small ones. Wastewater is the main issue for food plants, so expect questions about it.
- A building approval (Persetujuan Bangunan Gedung, PBG) before construction, and a certificate of fitness for use (Sertifikat Laik Fungsi, SLF) before operation.
- The industry business licence and the sector approvals for your product.
The sector approvals are where food plants differ. Packaged products need registration with the food and drug authority (BPOM), and the factory usually needs a good manufacturing practice certificate. Halal certification is mandatory for most food sold in Indonesia. Plants handling meat, poultry, eggs or fish need a veterinary control number or fisheries certification. The article on halal and food safety rules sets these out.
Expect each step to take longer than its official timeline, especially where a regency office has to inspect the site.
Raw material supply
A plant that runs below capacity loses money, and in Kalimantan supply is usually the reason it does. Most farms and fishing operations are small. Their output varies by season, quality varies by farm and they often sell to whoever pays cash first.
Plants manage this in a few ways:
- Contract farming, where the plant supplies seed, inputs or advice and agrees to buy at a set price or formula. It works when the plant pays reliably and the price beats the local traders often enough.
- Collection networks, with local agents who buy from many small producers and deliver in bulk.
- Their own farms or estates, which give control but tie up capital in land.
- Shipped-in or imported ingredients, which bring steady quality but expose the plant to freight costs and, for some products, import quotas set through the commodity balance (neraca komoditas). Sugar, salt, beef and some grains are among the products whose imports are controlled.
Whatever the model, ask for evidence of supply at the volume the plant needs, not just a list of farms in the area.
Power, water and waste
Food plants use a lot of power for cooking, drying, freezing and packing, and many need it around the clock. Get a written statement from the state electricity company (PLN) on what it can supply and from when. Plan for backup generators.
Water is the next constraint. Many processes need clean water in volume, and some sites in Kalimantan have only river or peat water that needs treatment. A permit may be needed to draw groundwater or surface water.
Wastewater from food processing is high in organic matter. It needs treatment before discharge, and the environmental approval will set the standard. Untreated or poorly treated effluent smells, leaks into rivers and draws complaints from the villages downstream.
Getting the finished product to buyers is its own cost. The article on cold chain and food logistics covers the routes and the ports.
Incentives
Some investments in processing qualify for tax incentives, such as the tax allowance for certain business lines and locations, or the incentives inside a special economic zone. Eligibility depends on the KBLI code, the size of the investment and the location, and the rules are revised from time to time. Ask a tax adviser whether your project qualifies before you count on any of them.
What to check first
Before you commit to a site or a plant design, get these:
- The zoning of the site in writing, and confirmation that it isn’t protected farmland or forest area.
- The KBLI codes for every product, checked against the positive list for foreign ownership limits.
- A supply plan with volumes per month, sources and evidence that those sources will sell to you.
- Written answers from PLN on power and from the relevant agency on water and wastewater discharge.
- A list of the sector approvals each product needs, with the agency and an honest timeline for each.
If the supply plan is thin, fix it before anything else. A plant can be built in a year, but a reliable supply takes longer.
General information, not legal, tax or investment advice. Rules change, so confirm the current regulation with a notary or lawyer before you act.